PM 691 Park Student Business Discussion
Order Number Y47874HDUEW Type of Project Essay/Research Paper Writer Level PHD/MASTERS Writing Style APA/Harvard/MLA/CHICAGO Citations 5 Page Count 3-15 Description/Paper Instructions
PM 691 Park Student Business Discussion
Please respond to each student 150-200 words use references
Here is the original post for reference
After reading this week’s material, engage in an active discussion regarding the various type of schedule Compression Techniques and note the differences between crashing and fast tracking. Also, denote the key components of each method.
Please find an additional reference source and cite the source in your discussion post. Sources must be used to enhance the learning experience. By finding a referenced source, you are enhancing the learning experience by searching for another source of information on the topic. Also, please ensure you are using a source that is peer reviewed to ensure accuracy of information (select peer-reviewed journal articles in the Park Library).
Your original post should be in the format of an executive summary (must contain verbiage and bullet points to name the key points). Use APA formatting.
Here is what my teacher said this will be student 1 response
Ashley,
I see schedule compression is more of a technique than a methodology but I understand the change in the PMBOK. The major thing to notes is the difference between crashing and fast tracking and knowing when to use them. Can you think of an example where you would use crashing vs fast tracking?
Dr. J
Student 2
No matter how well a project is planned, actual durations of tasks can take longer than planned (PM Lydia, ND). Schedule Compression techniques are used to shorten the project schedule duration without reducing the project scope, in order to meet the project deadline (Usmani,2021).
Projects are often delayed and there are various reasons for that (Hornelen, Willy, 2005). In such cases it’s need to compress the project schedule duration in order to bring the project back on track (Hornelen, Willy, 2005). Fast tracking and Crashing are techniques used to compress project schedule (Hornelen, Willy, 2005).
Fast Tracking does not involve costs, but may result in risks and rework (Hornelen, Willy). In Crashing, additional resources are used to do things faster, thereby reducing duration. Although, crashing does not result in too much risks, but it involves cost (PM Lydia, ND).
Fast Tracking: Activities or phases normally done in a sequence, are done in parallel, for at least a portion of their duration (Usmani,2021). In this method, the Critical path is first reviewed (PM Lydia, ND). Also, all the activities that can be performed by overlapping are identified making sure any of these are compromising the Project Scope (PM Lydia, ND).
Crashing: This technique is used to shorten the schedule duration for the least incremental cost by adding resources (PM Lydia, ND). To do Crashing the Critical path is analyzed in order to Identify all the activities that can be completed early with the help of extra resources (PM Lydia, ND). It is important to identify the activities that provides the highest compression at the least possible cost (Hornelen, Willy, 2005).
Resources
Fahad Usmani (09/02/2021) Fast-Tracking vs Crashing – Schedule Compression Techniques. Retrieved from: https://pmstudycircle.com/fast-tracking-crashing-schedule-compression-techniques-in-time-management/ (Links to an external site.)
PM Lydia (ND) Fast Tracking vs Crashing – Schedule Compression Techniques Retrieved from: https://pmvidya.com/blog/fast-tracking-vs-crashing-project-schedule-compression-techniques/ (Links to an external site.)
Hornelen, Willy (2005) PRODUCTION AND OPERATIONS
Student 3
Lina,
You have mentioned some good points. In the following, I will share the content that I find useful with the class.
Algorithm for reducing project duration or project critical path compression:Path: An interconnected set of activities, the first of which does not require a prerequisite and the last does not require a posterior.
Critical Path: The path whose last activity is equal to the project completion date.
Compression: Reduces the time required to runCandidate activity for compression: Activities that have the following conditions:
Technically capable of compression.
Their compression has the least negative consequences (such as: cost, etc.) and the most positive consequences (such as: profit, etc.).
Compressing them will cause at least one critical path to be compressed.Project critical path compression algorithm
For this purpose, the following steps are performed in order:
Identify project network routes
Identify critical project paths
Identify candidate activities
Select a set of candidate activities whose compression will simultaneously compress all critical paths.
Compression of selected activities in the previous step, until either a new critical path is created or sufficient compression is performed.References:
Larson, E. W., & Gray, C. F. (2021). Project Management: The Managerial Process. New York: McGowan-Hill.
Abu Warda, Zineb, Hegazi, Tarek. (2019). Multi-dimensional optimization model for schedule fast-tracking without over-stressing construction workers. (Park University Library).
PM 691 Park Student Business Discussion
Excellent The essay demonstrates exemplary comprehension of the relevant content by thoroughly as well as correctly discussing the relevant information; identifying as well as explaining all of the 3 fundamental aspects; using correct terminology; describing the reasoning next to key points/claims; as well as substantiating points with several accurate as well as illuminating examples, as necessary or useful. There are no gaps in the necessary answer. Good Scholarly sources that are credible are employed to successfully support statements that are, as the most part, clear as well as fairly expressed. With just a few minor inaccuracies, APA 6th Edition is utilized. There are a few small typos in the references and/or citations. There is some reliance on dubious sources. Satisfactory Because of certain improper terminology and/or confusing wording, the work is frequently confused and difficult to understand; thoughts may be disjointed, meandering, and/or repetitious. a lack of structure; and/or grammatical, spelling, and punctuation mistakes. Poor The essay demonstrates a lack of understanding of the related documents by failing to address or improperly addressing the relevant; failing to identify or incorrectly trying to explain key concepts/ideas; ignoring as well as incorrectly attempting to explain key points/claims as well as the rationale behind them; and/or inaccurately or improperly using terminology. No Response Essay displays great writing abilities, such as a clear as well as thought-provoking thesis, suitable and effective organization, vibrant and persuasive supporting materials, good diction as well as sentence skills, and faultless or almost perfect mechanics, such as spelling and grammar. The essay flawlessly achieves the assignment’s objectives. Quality of Response Because of its intelligent growth and mature manner, this study merits attention. It provides a compelling analysis of or reaction to the text, expanding on that response using well-chosen examples and arguments. The sixth paper demonstrates that its author can typically use appropriate words, employ advanced phrases successfully, and adhere to written English rules. Delivery Timeline 3 hours – 24 hours Backlinks www.crucialessay.com/orders/ordernow/www.contentexpertagencies.com/orders/ordernow
Tired of getting an average grade in all your school assignments, projects, essays, and homework? Try us today for all your academic schoolwork needs. We are among the most trusted and recognized professional writing services in the market.
We provide unique, original and plagiarism-free high quality academic, homework, assignments and essay submissions for all our clients. At our company, we capitalize on producing A+ Grades for all our clients and also ensure that you have smooth academic progress in all your school term and semesters.
High-quality academic submissions, A 100% plagiarism-free submission, Meet even the most urgent deadlines, Provide our services to you at the most competitive rates in the market, Give you free revisions until you meet your desired grades and Provide you with 24/7 customer support service via calls or live chats.